How long a custom yacht takes to build depends on its size, its complexity and how much is changed from the base design. For a Bekkers yacht, the yard confirms the lead time from signed contract to delivery in your quote. Across the industry, a hand-built yacht of 40 to 60 ft typically takes many months rather than weeks, because every hull is welded, faired, painted and outfitted by hand.
Below we walk through each stage, from the first conversation to the sea trial, and explain what speeds a build up and what slows it down.
Why a custom build takes time
Most yachts in the 40 to 60 ft range are built in series from fibreglass moulds. Once the mould exists, hulls can be produced in a steady rhythm. Bekkers Yachts works differently: no mass production, no fibreglass hull, no restrictions. Every yacht is built in aluminium, by hand, for one owner.
That brings freedom: any colour combination, any interior material on request, and the engine package you prefer. It also means there is no shortcut. Plates are cut, formed and welded. Welds are ground and faired until they disappear; Motor Boat & Yachting noted that there were no visible weld marks on the AZUR 45. That level of finish is a matter of hours, not of automation.
The stages of a custom yacht build
| Stage | What happens |
|---|---|
| 1. Brief | First conversation, how and where you will use the yacht |
| 2. Design and specification | Model choice, layout, engines, colours, materials, options |
| 3. Contract and build slot | Agreement on specification, price and delivery |
| 4. Hull and superstructure | Aluminium cutting, welding, fairing and paint |
| 5. Outfitting | Engines, systems, interior, deck equipment |
| 6. Sea trial and delivery | Testing, handover, transport |
1. The brief
Every build starts with a conversation. Where will you keep the yacht? Day trips or weekends on board? How many guests? This is when you can speak with Leon Bekkers and the team directly, at the yard or at an event. The yard replies personally to every enquiry within one working day, so this stage moves as fast as you want it to.
2. Design and specification
Next, the yacht takes shape on paper. You choose the model: the AZUR 45HT hardtop weekender, the Beachclub 40 or the Carib 64HT flagship. Then come the choices that make it yours. On the AZUR 45 that includes the engine package, from 2x Volvo Penta IPS 600 (2x 440 hp) to 2x IPS 800 (2x 600 hp), the paint to sample, hardtop options such as a panoramic sliding roof, and the interior wood and marine leather or any other material on request.
This stage typically takes longer when the changes are bigger. Choosing a colour is quick. Reworking a layout involves the designer, René van der Velden, and the naval architects, and takes more time.
3. Contract and build slot
Once the specification is agreed, it is fixed in a contract with price and delivery date. Because every yacht is built by hand, the start of your build depends on the slots available. The payment schedule is set out in the build contract.
4. Hull and superstructure
This is where aluminium becomes a yacht. The hard chine hull is built from plate, welded and faired. The superstructure follows, such as the aluminium hardtop on the AZUR 45HT. Paint is applied in your chosen colours. Aluminium suits this way of building: it can be shaped and welded precisely without a mould, which is exactly what allows each yacht to be different.
5. Outfitting
With the hull painted, the yacht is fitted out. Engines and IPS drives go in. Fuel, water and electrical systems are installed. On the AZUR 45HT that means 1,240 l of fuel, 278 l of fresh water and 165 l of black water capacity. The interior is built: cabins, bathroom, wood and leather. On deck, the Flexiteek, sun beds, outdoor galley, electric swim ladder and lighting are fitted.
Outfitting is often the longest stage in any yacht build, because it involves the most trades and the most detail. Late changes here typically have the biggest effect on timing.
6. Sea trial and delivery
Before handover, the yacht is tested on the water. Sea trials take place at the yard in Heusden, on the river Maas. Systems are checked, performance is verified and any final adjustments are made. Then the yacht is handed over, or prepared for transport to its home port. Ask the yard about delivery and transport to your home port.
For a closer look at what happens in each stage on the workshop floor, read how a custom yacht is built.
What affects the lead time
Several factors typically decide how long your build takes:
- Size. The Carib 64HT, at 18.7 m with three cabins and three bathrooms, involves far more work than the 13.5 m AZUR 45.
- Degree of customisation. Colour and material choices rarely change the timeline. Layout changes or new equipment do.
- Decisions on time. A build moves fastest when choices are made before the relevant stage begins.
- Supply of equipment. Engines and specialist equipment come from suppliers with their own lead times.
- Yard capacity. Every hull is built by hand, so the start date depends on available slots.
Planning your season
If you want to be on the water for a particular summer, it helps to start the conversation early. Ask the yard about current build slots and the realistic delivery date for your chosen model.
Frequently asked questions
How long does it take to build a Bekkers yacht?
The lead time from contract to delivery depends on the model, the degree of customisation and the available build slots. The yard can give you a realistic date for your specification.
Why does a custom aluminium yacht take longer than a production boat?
Production boats are typically built in series from fibreglass moulds. A Bekkers yacht is built by hand in aluminium for one owner, so each hull is cut, welded, faired and painted individually, and the interior is made to your specification.
Can I change the specification during the build?
Changes are often possible, but they are easiest early in the process. Late changes during outfitting typically have the biggest effect on time and cost. How changes are handled is set out in the build contract.
Can I visit my yacht while it is being built?
The yard is at Heusden, in the south of the Netherlands, and owners are welcome to discuss visits with the team.
Where does the sea trial take place?
Sea trials take place at the yard in Heusden.